On April 12, 2010 the wall behind the auditorium at Mount Vernon High School collapsed. As a result several classrooms were destroyed including the TV Studio and Auto Shop classroom.
Reconstruction work is scheduled to take place in three phases. Please click on the progress schedule to see the details of each phase.
Progress Schedule.pdf
APRIL 2010
Photographs of the damage
View of back of auditorium
Damaged Classrooms
LATE APRIL 2010
Affected areas sealed off in the building

April 2010
Debris removal
SUMMER 2010
Abatement of affected areas
Column Reinforcement

OCTOBER 2010
Steel studs are installed

Late October 2010
Sheetrock installation